Best Mixed-Use Precast
As downtown Temple grows, so does the need for parking that supports both daily use and economic activity. The City of Temple – 4th Street Mixed Use Parking Garage is a six-level, two-bay precast structure that pairs ground-floor storefront retail with efficient parking above, using architectural precast detailing to fit seamlessly into the downtown context.
This award submission highlights the second of two parking structures delivered for the City of Temple, built with a coordinated design-assist approach between the contractor, architect, precaster, and specialty engineer.
Fast Facts
Award: Best Parking Structure – Mixed Use
Project: City of Temple – 4th Street Mixed Use Parking Garage
Location: 301 South 4th Street, Temple, TX 76502
Structure: 6 levels, 2 bays wide
Parking Capacity: 415 vehicles
Precast Scope: 605 precast/prestressed pieces
Suspended Double Tees: 144,230 SF
Key program element: Ground-level mixed-use storefront retail + speed ramp to levels 2–6
Project OverviewSpawGlass was awarded the contract to build two downtown parking structures for the City of Temple, including substantial site work and utility relocation. Given the schedule, complexity, and architectural detailing, the contractor selected one precaster for both projects and engaged Legacy Precast in spring 2021 to support design/build coordination.
Precast Scope and SystemsThe garage includes 144,230 SF of suspended double tees and accommodates 415 vehicles. A speed ramp provides access to parking on levels two through six. The precast scope totaled 605 pieces, delivered and erected ahead of schedule and within budget.
Precast components (counts):
221 double tees
94 spandrels
87 walls
60 architectural walls
41 horizontal ramp walls
20 beams
12 shear walls
42 columns
23 stairs
Architectural Finishes and Downtown Fit
Key architectural features included:
Cast-in thin brick with two brick patterns: running bond + basket weave
Architectural concrete mix with a medium sandblast finish
Multiple face projections, eyebrows, recesses, and reveals to meet the architect’s design intent.
Mixed-Use Performance and DurabilityBecause the ground level is dedicated to retail, waterproofing and long-term performance were critical:
Waterproofing of the field-topped double tee system above the mixed-use retail space
A field-topped double tee approach supported consistent topping placement and drainage, eliminating over 13,860 LF of caulking and long-term joint maintenance for the owner.
Coordination and DeliveryAfter kickoff, SpawGlass coordinated design meetings with Legacy Precast, CEG (precast specialty engineer), and Garcia Architects. Legacy Precast led optimization efforts alongside CEG’s modeling, detailing, and piece ticketing to support the manufacturing of the complex structure.
Schedule challenges from underground utility relocation pushed the original precast schedule out, but the team re-adapted the timeline: contract executed in 2021, production in 2022, installation completed in 2023, and the structure officially opened in 2025.
At the ribbon cutting in April 2025, Temple Assistant City Manager David Olson noted the facility “offers a solution to current and future parking challenges while supporting the ongoing development of our city.”
Project Team:
- Precast Concrete Manufacturer: Legacy Precast LLC (Brookshire, TX)
- General Contractor: SpawGlass (College Station, TX)
- Precast Concrete Engineer: Consulting Engineers Group (CEG) (San Antonio, TX)
- Architect: Garcia Architects (Belton, TX)
- Subcontractor (Erector): SnS Erectors (Burleson, TX)
PCMA Associates
ALP Supply • Arcosa Lightweight • Consulting Engineers Group (CEG) • Hamilton Form Company, Ltd • Insteel Wire Products • JVI • Master Builders Solutions • MI-JACK Products • Nox-Crete Products Group • Oklahoma Steel & Wire • SnS Erectors, Inc. • Splice Sleeve North America • Texas Lehigh Cement Company, LLC
FAQ
What is the City of Temple 4th Street Mixed Use Parking Garage?
A six-level, two-bay precast parking structure in downtown Temple, Texas, with ground-floor storefront retail and parking on levels two through six.
How large is the precast scope?
The project includes 144,230 SF of suspended double tees and 605 precast/prestressed pieces. CMA BIP 2025 City of Temple Su…
What architectural finishes were used?
Cast-in thin brick (running bond and basket weave patterns) plus a medium sandblast architectural concrete finish, with projections, recesses, and reveals. CMA BIP 2025 City of Temple Su…
Why was waterproofing important here?
The first suspended level sits above mixed-use retail space, requiring waterproofing of the field-topped double tee system. CMA BIP 2025 City of Temple Su…
How does the design reduce long-term maintenance?
The field-topped double tee system improved drainage and eliminated over 13,860 LF of caulking and joint maintenance.















