Best Parking Structure – Public Use

Ft. Bend Town Center METRO Transit Parking Structure - Missouri City, Texas

BestinPrecast TROPHY 2025

The Ft. Bend Town Center METRO Transit Parking Structure is a new park-and-ride facility developed through a public-private partnership between METRO and NewQuest Properties, serving as an anchor for Phase 3 of Fort Bend Town Center in Missouri City, Texas.


The transit center provides curb-to-curb service with pickup/drop-off for regular trips to the
Texas Medical Center, Downtown Houston, the Galleria, and destinations across the region.


Fast Facts
  • Award: Best Parking Structure – Public Use

  • Project: Ft. Bend Town Center METRO Transit Parking Structure

  • Location: Missouri City, Texas

  • Structure: 6 levels | 3 bays wide

  • Capacity: 1,750 vehicles

  • Suspended double tees: 457,425 SF

  • Length: 518 feet

  • Expansion joint: through the structure and elevator core

  • Precast scope: 1,311 precast/prestressed pieces (10,000+ cy concrete placed)

  • Opened: January 27, 2025

  • Video runtime: ~2:06


Why precast (and why this project needed it)

METRO’s traditional design-bid-build approach has led to projects being delayed or shelved when budgets come in high. For this facility, the partnership structure and schedule demanded a solution that could be delivered fast, predictably, and with controlled costs.


Flintco
selected a design-build precast approach and awarded the work to Legacy Precast, enabling off-site production, just-in-time deliveries, and accelerated erection once foundations were ready.


Key design features
  1. Architectural finishes on structural components
    Architectural concrete mix with reveals and a medium sandblast finish.

  2. Expansion-joint detailing
    Stainless steel slip connections at the expansion joint in the central stair/elevator core.

  3. Canopy support (the “not your typical garage” problem)
    The structure was required to support a large cantilevered canopy at customer pickup/drop-off zones. Because canopy tieback loads landed at specific column locations, spandrels could not be pocketed in the typical way. The solution used
    exposed galvanized haunches at the column sides to support spandrels at those locations.

  4. Field-topped double tees for drainage + lifecycle savings
    Field-topped double tees created consistent topping and superior drainage while eliminating
    40,000+ LF of caulking and ongoing joint maintenance.


Precast components (type + count)

Total: 1,311 pieces

  • 653 Double tees

  • 204 Spandrels

  • 157 Walls

  • 120 Vertical ramp walls

  • 45 Beams

  • 24 Shear walls

  • 46 Columns

  • 50 Stairs

  • 12 Flat slabs


Schedule + delivery (fast-track performance)
  • Released for engineering: September 2023

  • Manufacturing began: January 2024

  • First piece erected: March 2024

  • Installation completed: August 2024 (despite 9 rainout days)

  • Opened: January 27, 2025


Legacy Precast delivered and erected the structure ahead of schedule and within budget, allowing the project team to avoid liquidated damages and open early.

 
Legacy Precast Logo

Project Team:

  • Precast Manufacturer: Legacy Precast (Brookshire, TX)
  • General Contractor: Flintco Construction (Houston, TX)
  • Precast Specialty Engineer: Consulting Engineers Group (CEG) (San Antonio, TX)

PCMA Associates

Arcosa • Conac • Consulting Engineers Group (CEG) • Hamilton Form Company • Insteel Wire Products • JVI • Master Builders Admixtures, Inc. • MI-Jack Products • Oklahoma Steel and Wire • Splice Sleeve North America, Inc. • Texas Lehigh Cement Co • WMC Steel, LLC

FAQ
 

What is the Ft Bend Town Center METRO Transit Parking Structure?
A six-level, three-bay precast park-and-ride garage in Missouri City, Texas, that anchors Fort Bend Town Center Phase 3 and supports METRO commuter bus service.


How many vehicles does it accommodate?

Approximately 1,750 vehicles.


How big is the precast scope?

1,311 precast/prestressed pieces, including 457,425 SF of suspended double tees and over 10,000 cubic yards of concrete placed.


What was a key structural challenge?

Supporting a large cantilevered canopy at pickup/drop-off zones required non-typical connections, using exposed galvanized haunches where spandrels couldn’t be pocketed at columns.


How does the design reduce long-term maintenance?

Field-topped double tees improved drainage and eliminated more than 40,000 LF of caulking and joint maintenance for the owner. 

See our other Best in Precast 2025 Winners