Best Parking Structure – Public Use
The Ft. Bend Town Center METRO Transit Parking Structure is a new park-and-ride facility developed through a public-private partnership between METRO and NewQuest Properties, serving as an anchor for Phase 3 of Fort Bend Town Center in Missouri City, Texas.
The transit center provides curb-to-curb service with pickup/drop-off for regular trips to the Texas Medical Center, Downtown Houston, the Galleria, and destinations across the region.
Fast Facts
Award: Best Parking Structure – Public Use
Project: Ft. Bend Town Center METRO Transit Parking Structure
Location: Missouri City, Texas
Structure: 6 levels | 3 bays wide
Capacity: 1,750 vehicles
Suspended double tees: 457,425 SF
Length: 518 feet
Expansion joint: through the structure and elevator core
Precast scope: 1,311 precast/prestressed pieces (10,000+ cy concrete placed)
Opened: January 27, 2025
Video runtime: ~2:06
Why precast (and why this project needed it)METRO’s traditional design-bid-build approach has led to projects being delayed or shelved when budgets come in high. For this facility, the partnership structure and schedule demanded a solution that could be delivered fast, predictably, and with controlled costs.
Flintco selected a design-build precast approach and awarded the work to Legacy Precast, enabling off-site production, just-in-time deliveries, and accelerated erection once foundations were ready.
Key design features
Architectural finishes on structural components
Architectural concrete mix with reveals and a medium sandblast finish.Expansion-joint detailing
Stainless steel slip connections at the expansion joint in the central stair/elevator core.Canopy support (the “not your typical garage” problem)
The structure was required to support a large cantilevered canopy at customer pickup/drop-off zones. Because canopy tieback loads landed at specific column locations, spandrels could not be pocketed in the typical way. The solution used exposed galvanized haunches at the column sides to support spandrels at those locations.Field-topped double tees for drainage + lifecycle savings
Field-topped double tees created consistent topping and superior drainage while eliminating 40,000+ LF of caulking and ongoing joint maintenance.
Precast components (type + count)Total: 1,311 pieces
653 Double tees
204 Spandrels
157 Walls
120 Vertical ramp walls
45 Beams
24 Shear walls
46 Columns
50 Stairs
12 Flat slabs
Schedule + delivery (fast-track performance)
Released for engineering: September 2023
Manufacturing began: January 2024
First piece erected: March 2024
Installation completed: August 2024 (despite 9 rainout days)
Opened: January 27, 2025
Legacy Precast delivered and erected the structure ahead of schedule and within budget, allowing the project team to avoid liquidated damages and open early.
Project Team:
- Precast Manufacturer: Legacy Precast (Brookshire, TX)
- General Contractor: Flintco Construction (Houston, TX)
- Precast Specialty Engineer: Consulting Engineers Group (CEG) (San Antonio, TX)
PCMA Associates
Arcosa • Conac • Consulting Engineers Group (CEG) • Hamilton Form Company • Insteel Wire Products • JVI • Master Builders Admixtures, Inc. • MI-Jack Products • Oklahoma Steel and Wire • Splice Sleeve North America, Inc. • Texas Lehigh Cement Co • WMC Steel, LLC
FAQ
What is the Ft Bend Town Center METRO Transit Parking Structure?
A six-level, three-bay precast park-and-ride garage in Missouri City, Texas, that anchors Fort Bend Town Center Phase 3 and supports METRO commuter bus service.
How many vehicles does it accommodate?
Approximately 1,750 vehicles.
How big is the precast scope?
1,311 precast/prestressed pieces, including 457,425 SF of suspended double tees and over 10,000 cubic yards of concrete placed.
What was a key structural challenge?
Supporting a large cantilevered canopy at pickup/drop-off zones required non-typical connections, using exposed galvanized haunches where spandrels couldn’t be pocketed at columns.
How does the design reduce long-term maintenance?
Field-topped double tees improved drainage and eliminated more than 40,000 LF of caulking and joint maintenance for the owner.















